Place of Assembly permits in NYC: real approval times

Place of Assembly filings in NYC, measured across every DOB filing on record. These are the real numbers, not the published targets.

33,614
filings on record
48 days
median to approval
349 days
worst case (p90)
14.4%
of all filings disapproved
32.0%
professionally certified
Filing a Place of Assembly job? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.