Permit stats · Bronx

Place of Assembly permits in Bronx: real approval times

Place of Assembly filings in Bronx, measured across every DOB filing on record. These are the real numbers, not the published targets.

3,892
filings on record
5 days
median to approval
278 days
worst case (p90)
12.5%
of all filings disapproved
45.7%
professionally certified

Bronx vs citywide, median days to approval

Bronx
5d
NYC
48d
Filing a Place of Assembly job in Bronx? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.