Permit stats · Manhattan

Place of Assembly permits in Manhattan: real approval times

Place of Assembly filings in Manhattan, measured across every DOB filing on record. These are the real numbers, not the published targets.

13,418
filings on record
64 days
median to approval
365 days
worst case (p90)
14.7%
of all filings disapproved
30.9%
professionally certified

Manhattan vs citywide, median days to approval

Manhattan
64d
NYC
48d
Filing a Place of Assembly job in Manhattan? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.