Condo subdivision permits in Manhattan: real approval times

Subdivision (condo) filings in Manhattan, measured across every DOB filing on record. These are the real numbers, not the published targets.

3,995
filings on record
21 days
median to approval
81 days
worst case (p90)
4.7%
of all filings disapproved
33.2%
professionally certified

Manhattan vs citywide, median days to approval

Manhattan
21d
NYC
20d
Filing a Condo subdivision job in Manhattan? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.