Permit stats · Brooklyn

Demolition permits in Brooklyn: real approval times

Demolition filings in Brooklyn, measured across every DOB filing on record. These are the real numbers, not the published targets.

24,506
filings on record
0 days
median to approval
11 days
worst case (p90)
0.0%
of all filings disapproved
0.3%
professionally certified

Brooklyn vs citywide, median days to approval

Brooklyn
0d
NYC
0d
Filing a Demolition job in Brooklyn? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.