Permit stats · Bronx

Subdivision permits in Bronx: real approval times

Subdivision (improved) filings in Bronx, measured across every DOB filing on record. These are the real numbers, not the published targets.

2,092
filings on record
20 days
median to approval
238 days
worst case (p90)
20.5%
of all filings disapproved
35.9%
professionally certified

Bronx vs citywide, median days to approval

Bronx
20d
NYC
12d
Filing a Subdivision job in Bronx? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.