Permit stats · Bronx

New building permits in Bronx: real approval times

New Building filings in Bronx, measured across every DOB filing on record. These are the real numbers, not the published targets.

25,982
filings on record
89 days
median to approval
447 days
worst case (p90)
5.8%
of all filings disapproved
37.7%
professionally certified

Bronx vs citywide, median days to approval

Bronx
89d
NYC
67d
Filing a New building job in Bronx? Run the free Pre-Flight check to see your job's lane, likely objections, and realistic timeline before you file.

Methodology: computed from DOB Job Application Filings (ic3t-wcy2) via NYC Open Data, refreshed with each data build. Median and p90 measure pre-filing date to approval on approved jobs. Full methodology on the Intelligence page.